Mecklenburg Middle & High School
When you’re building a 170-acre school property, you need a huge amount of concrete. For this regional school in southern Virginia, Silverback poured 3,000 cubic yards of footers in a mere five weeks. We had three excavators running twelve hours a day, pouring 200 cubic yards every afternoon. One requirement was that we would pour concrete within 24 hours of opening footers, and we hit that target every time, pouring over 700 cubic yards per week.
Owner | Mecklenburg County |
Location | Baskerville, VA |
Completed | Ongoing |
Size | 9,000+ CY |
Contractor | Cleveland Construction |
Scope | Footers, Slab on Grade, Slab on Decks |